Due to weather, the Mill and Inlay work previously scheduled for Friday, June 19, 2015 has been delayed.

The schedule for June 22 – July 10, weather permitting, is as follows:

June 22  Westwood Road – Cloud St and Teakwood St

June 29 – July 1 Front Street - Republic Ave to Crawford St

July 2  Beach Street – Cloud St to Winona St

July 6  Westwood Road – Cloud St to Teakwood St

July 7  Winona Street – Westwood Rd to Dover Dr

July 8 – 9  Teakwood Street – Westwood Rd to Rover Dr

July 9 – 10  Dover Drive – Teakwood St to Cloud St

While the work is in progress, individual roads will be closed to through traffic. The contractor will begin setting traffic control at 7 am. Residences and businesses will be notified prior to changes in access to properties. On-street parking in work zones will be prohibited. Any vehicles, or equipment, left on the street on the day paving is scheduled may be towed at the owners’ expense.

This project is a major component of the 2015 Street Maintenance Program. The project consists of milling the existing asphalt street surface 1.5” deep and then resurfacing it with new asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed shortly after resurfacing is complete.