News Releases

8/10/2018 - Mill and Inlay Work Continues

On Monday through Friday, August 13 to 17, APAC Shears of Salina will continue work on the City of Salina's annual asphalt mill and inlay project. The schedule is as follows, weather permitting:

Milling:

M

T

W

TH

F

13

14

15

16

17

9th, North to Pacific

M

T

W

TH

F

9th, Pacific to Euclid

M

T

W

TH

F

Paving:

M

T

W

TH

F

13

14

15

16

17

5th, Grand to Harsh

M

T

W

TH

F

Woodland, 9th to 2nd

M

T

W

TH

F

The work consists of milling the existing asphalt street surface 1.5" and replacing it with new asphalt to rehabilitate and preserve the pavement section. Permanent pavement markings will be placed shortly after the resurfacing.

The work will be completed with lane closures. Residents and business owners will be notified prior to changes in access to properties. On-street parking in work zones will be prohibited. Any vehicles or equipment left on the street on the day paving is scheduled may be towed at the owner's expense.

The $1.5 million project is a major component of the City of Salina's $4.7 million 2018 maintenance capital improvement program.