4/29/2019 - Santa Fe Avenue Streetscape & Waterline Update

Weather dependent, the outlook for Santa Fe progress is as follows:

 

Dates

Status

Pavement, curb and structures have been removed Iron to Ash (eash half)

4/22-4/26

Ongoing sidewalk replacement

Watermain, Fire protection and services Iron to Ash (east half)

4/22-6/10

Watermain will continue Monday

Iron to Ash 8 foot sidewalk

4/25-5/10

Waiting on removals

Iron intersection East West Traffic Open

5/3

Open with limited parking

Southeast Ash Quadrant Closure

5/4-5/24

 

Open northbound traffic on Santa Fe, Walnut to Iron

5/4

Limited parking on the east side of Santa Fe

Close the southeast quadrant – Ash & Santa Fe

5/3-6/1

Westbound traffic allowed on Ash. Northbound will continue to detour at Iron

All businesses in this work area will have access to their doors. Plenty of downtown parking exists in the public parking lots and along Fifth Street and Seventh Street.

Smoky Hill Construction is a Salina based company working with the city to improve downtown Salina. For questions, contact Rick Brown, Public Relations at Smoky Hill Construction, at (785) 819-6316.