News Releases

8/23/2013 - Magnolia Road and Belmont Boulevard Intersection Replacement

Contact: Kent Johnson
Civil Engineer
Public Works Department
785-309-5725
kent.johnson@salina.org

 Magnolia Road and Belmont Boulevard
Intersection Replacement to Begin

On Monday, August 26, 2013, Pavers Inc. of Salina will begin removal and replacement of the pavement at the Magnolia Road and Belmont Boulevard intersection.

The first phase of work will be to replace the north half of the intersection. Two-way traffic will be reduced to single lanes in both directions on Magnolia Road, while Belmont Boulevard north of Magnolia Road will be closed to through traffic. Signage will be posted clearly marking traffic restrictions, including prohibiting left turns at the intersection throughout the duration of the project. Access to properties will be maintained.

Work is expected to last approximately six weeks, weather permitting. Motorists should expect significant traffic delays and consider alternate routes.